Groundbreaking

December 17, 2025

St. Paul Catholic Church and St. Hubert Parish broke ground Tuesday for the new Parish Hall! Thank you to everyone who was able to come out on this beautiful day to experience the joy of seeing a project come to life. This is an exciting time for all of us to come together and show our support!

Construction begins

January 15, 2026

Construction of our St. Hubert parish center began on January 2, 2026. The ground was prepped, foundations and footings were poured and this week a gravel base was laid for the building’s floor. Keep watching for more updates in the coming weeks.

Installing Utilities

February 27, 2026

We are making progress on the new parish hall! Underground plumbing and electrical were started this week!

Pouring Concrete

March 24, 2026

The concrete has been poured. The concrete specialists are busy leveling and smoothing the edges. Now drying time so that the concrete can cure.

Material Delivery

April 6, 2026

Building materials have arrived!

Trusses Arrive

April 9, 2026

The building trusses arrived today! So excited to see this to completion!

Installing Post Brackets 

April 10, 2026

This morning the guys started early and installed the post brackets. Stay tuned for next week’s progress…

Building Walls 

April 13, 2026

Morton Building workers started early again. Today they are building walls.

Installing Posts 

April 14, 2026

THE FIRST POSTS ARE UP!!! Progress!

We Have Walls! 

April 14, 2026

This morning’s progress…

We Have More Walls! 

April 14, 2026

This afternoon’s progress. They are preparing for the truss installation and we have walls for the entrance. Woohoo!

It’s Starting to Look Like a Parish Hall 

April 17, 2026

This afternoon’s progress. The office area (left side of picture 2 and 3) was mostly done by noon. Moving right along…

Trusses Going In 

April 17, 2026

Most of the trusses are in place! They have tied them together and installed the stingers(the piece for the soffit installation). So much progress this week!

Soffit Installation 

April 17, 2026

Finishing work on Friday with soffit installation.

Window Framing

April 21, 2026

Today’s accomplishments-more soffits and window framing.

Soffit Completion

April 21, 2026

The soffits are done in the hall area and most of the office area. The beams have been added to the main entrance roof.

Sheathing the Exterior

April 21, 2026

Lots of activity this afternoon! The north side lower soffit was installed along Jackson St. exterior light installation began on the south and west soffits. All of the arch windows framing was done. They started sheathing the exterior. All of the doors were cut out.

Roof Work Begins

April 22, 2026

Roof work this morning!