Groundbreaking
December 17, 2025
St. Paul Catholic Church and St. Hubert Parish broke ground Tuesday for the new Parish Hall! Thank you to everyone who was able to come out on this beautiful day to experience the joy of seeing a project come to life. This is an exciting time for all of us to come together and show our support!
Construction begins
January 15, 2026
Construction of our St. Hubert parish center began on January 2, 2026. The ground was prepped, foundations and footings were poured and this week a gravel base was laid for the building’s floor. Keep watching for more updates in the coming weeks.
Installing Utilities
February 27, 2026
We are making progress on the new parish hall! Underground plumbing and electrical were started this week!
Pouring Concrete
March 24, 2026
The concrete has been poured. The concrete specialists are busy leveling and smoothing the edges. Now drying time so that the concrete can cure.
Material Delivery
April 6, 2026
Building materials have arrived!
Trusses Arrive
April 9, 2026
The building trusses arrived today! So excited to see this to completion!
Installing Post BracketsÂ
April 10, 2026
This morning the guys started early and installed the post brackets. Stay tuned for next week’s progress…
Building WallsÂ
April 13, 2026
Morton Building workers started early again. Today they are building walls.
Installing PostsÂ
April 14, 2026
THE FIRST POSTS ARE UP!!! Progress!
We Have Walls!Â
April 14, 2026
We Have More Walls!Â
April 14, 2026
It’s Starting to Look Like a Parish HallÂ
April 17, 2026
Trusses Going InÂ
April 17, 2026
Soffit InstallationÂ
April 17, 2026
Window Framing
April 21, 2026
Soffit Completion
April 21, 2026
Sheathing the Exterior
April 21, 2026
Roof Work Begins
April 22, 2026
















































































