Capital Campaign Begins
Our Capital Campaign for the new parish hall is now underway. Prayerfully consider supporting this important project as we continue building for the future of our parish community. Scan the QR code below to learn more and make your pledge online.
Groundbreaking
December 17, 2025
St. Paul Catholic Church and St. Hubert Parish broke ground Tuesday for the new Parish Hall! Thank you to everyone who was able to come out on this beautiful day to experience the joy of seeing a project come to life. This is an exciting time for all of us to come together and show our support!
Construction begins
January 15, 2026
Construction of our St. Hubert parish center began on January 2, 2026. The ground was prepped, foundations and footings were poured and this week a gravel base was laid for the building’s floor. Keep watching for more updates in the coming weeks.
Installing Utilities
February 27, 2026
We are making progress on the new parish hall! Underground plumbing and electrical were started this week!
Pouring Concrete
March 24, 2026
The concrete has been poured. The concrete specialists are busy leveling and smoothing the edges. Now drying time so that the concrete can cure.
Material Delivery
April 6, 2026
Building materials have arrived!
Trusses Arrive
April 9, 2026
The building trusses arrived today! So excited to see this to completion!
Installing Post Brackets
April 10, 2026
This morning the guys started early and installed the post brackets. Stay tuned for next week’s progress…
Building Walls
April 13, 2026
Morton Building workers started early again. Today they are building walls.
Installing Posts
April 14, 2026
THE FIRST POSTS ARE UP!!! Progress!
We Have Walls!
April 14, 2026
We Have More Walls!
April 14, 2026
Trusses Going In
April 17, 2026
It’s Starting to Look Like a Parish Hall
April 17, 2026
Soffit Installation
April 17, 2026
Window Framing
April 21, 2026
Soffit Completion
April 21, 2026
Sheathing the Exterior
April 21, 2026
Roof Work Begins
April 22, 2026
Roof Work Continues
April 23, 2026
East Side Roof Work
April 24, 2026
East Side Roof Work Continues
April 24, 2026
Noontime update with tar paper on the east side of the roof
Progress Continues
April 28, 2026
After taking time off for all of the rain yesterday, the crew is back at it today!
Sheathing Continues
April 29, 2026
Outside sheathing is almost complete. Tar paper is done on the east side and they have begun the west side.
Finishing the Sheathing
April 30, 2026
House wrap is almost done
May 1, 2026
Yesterday, the crew started putting up the house wrap. Today, hopefully they will be able to finish that project. Also working on the east side entrance/exit to the St. Francis garden.
Stay tuned!
East Entrance work
May 1, 2026
Working on the east entrance/exit to the St. Francis Garden.
House wrap is done
May 1, 2026
The house wrap is finished and a peak on the inside.
We have windows!
May 4, 2026
We have windows!! They are beautiful!!
May 4, 2026
Office windows are in. And part of the hall windows.
The bricks are here!
May 6, 2026
The first load of bricks arrived today.
The sprinkler system is going in
May 6, 2026
The last two days have been spent starting the installation of the sprinkler system.
The preparation for bricks
May 7, 2026
Preparing to start the brick work.
More bricks
May 11, 2026
Due to the rain Friday they were only able to tease us with what the brick will look like. Today, with sun shining they are back at it! Looks so good!!




















































































































