Capital Campaign Begins

Our Capital Campaign for the new parish hall is now underway. Prayerfully consider supporting this important project as we continue building for the future of our parish community. Scan the QR code below to learn more and make your pledge online.

Groundbreaking

December 17, 2025

St. Paul Catholic Church and St. Hubert Parish broke ground Tuesday for the new Parish Hall! Thank you to everyone who was able to come out on this beautiful day to experience the joy of seeing a project come to life. This is an exciting time for all of us to come together and show our support!

Construction begins

January 15, 2026

Construction of our St. Hubert parish center began on January 2, 2026. The ground was prepped, foundations and footings were poured and this week a gravel base was laid for the building’s floor. Keep watching for more updates in the coming weeks.

Installing Utilities

February 27, 2026

We are making progress on the new parish hall! Underground plumbing and electrical were started this week!

Pouring Concrete

March 24, 2026

The concrete has been poured. The concrete specialists are busy leveling and smoothing the edges. Now drying time so that the concrete can cure.

Material Delivery

April 6, 2026

Building materials have arrived!

Trusses Arrive

April 9, 2026

The building trusses arrived today! So excited to see this to completion!

Installing Post Brackets 

April 10, 2026

This morning the guys started early and installed the post brackets. Stay tuned for next week’s progress…

Building Walls 

April 13, 2026

Morton Building workers started early again. Today they are building walls.

Installing Posts 

April 14, 2026

THE FIRST POSTS ARE UP!!! Progress!

We Have Walls! 

April 14, 2026

This morning’s progress…

We Have More Walls! 

April 14, 2026

This afternoon’s progress. They are preparing for the truss installation and we have walls for the entrance. Woohoo!

Trusses Going In 

April 17, 2026

Most of the trusses are in place! They have tied them together and installed the stingers(the piece for the soffit installation). So much progress this week!

It’s Starting to Look Like a Parish Hall 

April 17, 2026

This afternoon’s progress. The office area (left side of picture 2 and 3) was mostly done by noon. Moving right along…

Soffit Installation 

April 17, 2026

Finishing work on Friday with soffit installation.

Window Framing

April 21, 2026

Today’s accomplishments-more soffits and window framing.

Soffit Completion

April 21, 2026

The soffits are done in the hall area and most of the office area. The beams have been added to the main entrance roof.

Sheathing the Exterior

April 21, 2026

Lots of activity this afternoon! The north side lower soffit was installed along Jackson St. exterior light installation began on the south and west soffits. All of the arch windows framing was done. They started sheathing the exterior. All of the doors were cut out.

Roof Work Begins

April 22, 2026

Roof work this morning!

Roof Work Continues

April 23, 2026

Today’s noon time update.

East Side Roof Work 

April 24, 2026

This morning we work on the east half of the roof.

East Side Roof Work Continues

April 24, 2026

Noontime update with tar paper on the east side of the roof

Progress Continues

April 28, 2026

After taking time off for all of the rain yesterday, the crew is back at it today!

Sheathing Continues

April 29, 2026

Outside sheathing is almost complete. Tar paper is done on the east side and they have begun the west side.

Finishing the Sheathing 

April 30, 2026

Work continues today to finish the sheathing of the exterior walls. Tar paper is up and done.

House wrap is almost done

May 1, 2026

Yesterday, the crew started putting up the house wrap. Today, hopefully they will be able to finish that project. Also working on the east side entrance/exit to the St. Francis garden.

Stay tuned!

East Entrance work

May 1, 2026

Working on the east entrance/exit to the St. Francis Garden.

House wrap is done

May 1, 2026

The house wrap is finished and a peak on the inside.

We have windows!

May 4, 2026

We have windows!! They are beautiful!!

May 4, 2026

Office windows are in. And part of the hall windows.

The bricks are here!

May 6, 2026

The first load of bricks arrived today.

The sprinkler system is going in

May 6, 2026

The last two days have been spent starting the installation of the sprinkler system.

The preparation for bricks

May 7, 2026

Preparing to start the brick work.

More bricks

May 11, 2026

Due to the rain Friday they were only able to tease us with what the brick will look like. Today, with sun shining they are back at it! Looks so good!!

Bricks are looking good

May 13, 2026

Noon time progress.

Bricks on the peak (and interior sprinkler system)

May 15, 2026

So this morning they finished the peak and then started on the north side of the office area along Jackson St.

Bricks on the north side

May 14, 2026

Today, the bricklayers approached the peak of the upper roof and prepared to brick the north face of the building. Work is also progressing on the interior sprinkler system.

Bricklaying continues

May 20, 2026

The sun came out and the bricklayers resumed their bricklaying. Materials have been delivered for the interior as well.

Roof is done

May 21, 2026

Bricks going up in the west side! The roof is done!

Bricks are looking good

May 22, 2026

This was yesterday’s progress. Now with the holiday weekend and a hint of rain, we wait until Tuesday for the work to resume.

Back to work after the holiday weekend.

May 26, 2026

The crew is back at it again today!

Interior & exterior progress

May 27, 2026

Wednesday morning’s completed work.

Insulation is going in

May 28, 2026

Back at it again Thursday morning! Wow!!

Interior walls and more brick work

May 28, 2026

Thursday afternoon’s work progress. Holy cow!!! Look at the interior “walls” and the brick work so far! Love the arched windows!!

More insulation and more brick work

June 1, 2026

The work from last Friday!

All in a Monday’s work

June 1, 2026

Monday’s progress.

The Hall has a ceiling!

June 2, 2026

Tuesday’s accomplishments: The west office windows have a brick arch and the hall has a ceiling!

Look at those arches

June 3, 2026

Wednesday’s accomplishments!

Progress continues

June 4, 2026

Thursday’s progress

Rain, rain went away, now we have some progress today!

June 9, 2026

Now that the rain has let up some, the bricklayers are back at work and have finished another section! Soon the north side will be added to the list of completed.

North peak brick work

June 11, 2026

After yesterday’s rain, the bricklayers are back at it still working on the north peak. Watch for the special addition to hopefully show up by the weekend. No more rain please.

Love the cross!

June 12, 2026

We have some of the interior walls and stay tuned for the unveiling.